At Huntington Middle School, the opportunity to learn extends far beyond the inside of the classroom. The new two-story Barth Athletics Complex will include a full sized CIF Regulation gymnasium for the campus, two Media Classrooms, Fitness Room, Boy’s and Girl’s Team Rooms, and a second-floor multi-purpose room.  These areas are designed to help facilitate the School’s and Community’s health, fitness, recreational programs and social events.

Construction Zone Map

Closure Map

Timeline

  • Anticipated Completion: August 2019

What's Happening

 
  • Week of December 11 - Work on the building foundation continues.  Structural work in the classrooms is on-going.
 
******** Monday December 18 - This is the first major concrete 
​delivery ​
for the
​Barth Athletics Complex ​
project. 
​Concrete t
rucks will be coming and going from the site using the Sherwood entrance the entire day. 
​S​
taff will be posted on the driveway and playground entrances to assist with the safe entry and exit of the concrete trucks.
 
  • Week of December 18th - Electrical work begins in the classrooms and interior framing continues.  Masonry work begins. 
 
 
 

 


 
 emailicon  smsicon
For timely email and SMS text updates on construction, traffic, project progress and other areas of local area impact, please sign up for "Barth Athletics Complex" at SMUSD Alerts
  
 
 
Project Information
Jim Fahey
Director, Maintenance & Operations
(626) 299-7000 x1313