Barth Athletics Complex

Barth Athletics Complex

Overview

At Huntington Middle School, the opportunity to learn extends far beyond the inside of the classroom. The new two-story Barth Athletics Complex will include a full sized CIF Regulation gymnasium for the campus, two Media Classrooms, Fitness Room, Boy’s and Girl’s Team Rooms, and a second-floor multi-purpose room.  These areas are designed to help facilitate the School’s and Community’s health, fitness, recreational programs and social events.

Parking Closure Map

6-9-17 Closure Map

Timeline

  • Anticipated Completion: August 2019

What's Happening

Upcoming Construction activities for the week of June 12:
  • Demolition of the building continues
  • Electrical hook up of interim housing buildings
 
Upcoming Construction Activities for the week of June 19
  • Demolition of building and site work continues
  • Removal of demolished materials begins onto Huntington Drive 
  • Installation of low voltage systems into interim housing buildings

 

 


 
 emailicon  smsicon
For timely email and SMS text updates on construction, traffic, project progress and other areas of local area impact, please sign up for "Barth Athletics Complex" at SMUSD Alerts
  
 
 
Project Information
Jim Fahey
Director, Maintenance & Operations
(626) 299-7000 x1313