San Marino Unified School District

Barth Athletics Complex

Barth Athletics Complex

Overview

At Huntington Middle School, the opportunity to learn extends far beyond the inside of the classroom. The new two-story Barth Athletics Complex will include a full sized CIF Regulation gymnasium for the campus, two Media Classrooms, Fitness Room, Boy’s and Girl’s Team Rooms, and a second-floor multi-purpose room.  These areas are designed to help facilitate the School’s and Community’s health, fitness, recreational programs and social events.

Construction Zone Map

Closure Map

Timeline

  • Anticipated Completion: August 2019

What's Happening

 
  • Week of January 15 - Work on the exterior masonry walls continues including electrical conduits be placed.  Structural work in the classrooms is on-going.  Building sewer installation is on-going.
 
******** Thursday January 17 and Friday January 18 - 
​The initial placement of concrete in the exterior masonry walls begins.  Concrete t
rucks will be coming and going from the site using the Sherwood entrance beginning at 7 am each day.  
​S​
taff will be posted on the driveway and playground entrances to assist with the safe entry and exit of the concrete trucks.  Work will concluded before school dismissal
 
  • Week of January 22 - Masonry work continues with additional concrete pours to be determined.  Electrical work continues in the new building.  Structural work is on-going for the classrooms. 
 
 
 

 


 
 emailicon  smsicon
For timely email and SMS text updates on construction, traffic, project progress and other areas of local area impact, please sign up for "Barth Athletics Complex" at SMUSD Alerts
  
 
 
Project Information
Jim Fahey
Director, Maintenance & Operations
(626) 299-7000 x1313