San Marino Unified School District

Barth Athletics Complex Project

BAC

Overview

At Huntington Middle School, the opportunity to learn extends far beyond the inside of the classroom. The new two-story Barth Athletics Complex will include a full-sized CIF Regulation gymnasium for the campus, two Media Classrooms, Fitness Room, Boy’s and Girl’s Team Rooms, and a second-floor multi-purpose room.  These areas are designed to help facilitate the School’s and Community’s health, fitness, recreational programs, and social events.

Construction Zone Map

Closure Map

Timeline

  • Anticipated Completion: August 2019

BAC Project Updates


What's Happening
  • Week of May 20 - Site concrete work continues.  Elevator installation continues.  Electrical work continues.  Interior painting continues.  Roofing continues.  Learning wall installation begins in classrooms.  Interior painting continues.  Curtain wall installation for lobby to begin. Exterior door installation begins. Ceramic tile installation continues.
  • Week of May 27 - Monday is Memorial Day.  Salute a Vet.  No work.  Site concrete continues.  Plumbing fixture installation continues. Electrical work continues.  Flooring in classrooms begins.  Curtain wall installation continues.

 
 emailicon  smsicon
For timely email and SMS text updates on construction, traffic, project progress and other areas of local area impact, please sign up for "Barth Athletics Complex" at SMUSD Alerts
  
 
 
Project Information
Jim Fahey
Director, Maintenance & Operations
(626) 299-7000 x1313