San Marino Unified School District

Barth Athletics Complex Project

BAC

Overview

At Huntington Middle School, the opportunity to learn extends far beyond the inside of the classroom. The new two-story Barth Athletics Complex will include a full-sized CIF Regulation gymnasium for the campus, two Media Classrooms, Fitness Room, Boy’s and Girl’s Team Rooms, and a second-floor multi-purpose room.  These areas are designed to help facilitate the School’s and Community’s health, fitness, recreational programs, and social events.

Construction Zone Map

Closure Map

Timeline

  • Anticipated Completion: August 2019

BAC Project Updates

 

What's Happening
  • Week of July 8 - Gym Flooring finish installation begins.  Electrical work continues.  HVAC continues.  Site clean and restoration begins.  Landscaping continues. Learning wall whiteboard installation.  Wrestling room acoustical panel installation.
  • Week of July 15 - Gym Flooring finish continues.  Electrical work continues.  HVAC for gym and wrestling finalizes.  Site clean and restoration continues. Wrestling room acoustical completes.

 
 emailicon  smsicon
For timely email and SMS text updates on construction, traffic, project progress and other areas of local area impact, please sign up for "Barth Athletics Complex" at SMUSD Alerts
  
 
 
Project Information
Jim Fahey
Director, Maintenance & Operations
(626) 299-7000 x1313