San Marino Unified School District

Barth Athletics Complex

Barth Athletics Complex

Overview

At Huntington Middle School, the opportunity to learn extends far beyond the inside of the classroom. The new two-story Barth Athletics Complex will include a full sized CIF Regulation gymnasium for the campus, two Media Classrooms, Fitness Room, Boy’s and Girl’s Team Rooms, and a second-floor multi-purpose room.  These areas are designed to help facilitate the School’s and Community’s health, fitness, recreational programs and social events.

Construction Zone Map

Closure Map

Timeline

  • Anticipated Completion: August 2019

What's Happening

 
  • Week of June 25 - Work on the exterior masonry walls at the classrooms and multi-purpose room continues.  Masons are placing steel into walls for the structural steel attachment.  Next grouting of walls to occur June 27.   
  • Week of July 2 - Masonry work continues with pours to be determined.  Structural steel work is scheduled to begin.  
  • HAPPY FOURTH OF JULY !!!!  No work.

 
 emailicon  smsicon
For timely email and SMS text updates on construction, traffic, project progress and other areas of local area impact, please sign up for "Barth Athletics Complex" at SMUSD Alerts
  
 
 
Project Information
Jim Fahey
Director, Maintenance & Operations
(626) 299-7000 x1313